Another trip down to Spike to see progress. As you will see by the photo's there has been a quiet significant growth of the machine for the building of the bridge , in working mans terms "It's bloody big " . Both Tower cranes are now up on both sides of the river, and on the Widnes side you will see.there is one concrete support and further up one with all the steel work nearly ready for the cncrete . Here are some of the photo's. Tower Cranes both sides of the river.
The Building Machine
These are placed inside the machine onto which the cement is poured These photo's were taken from the back of the offices on Waterloo Road. The end view of the machine
Sorry , here's the bridge supports I
missed out
Thanks for looking
|
|